One development phase, planned at eight weeks. Two conversations.
Week 4, Steering Committee
Project manager: We have spent exactly what we planned to have spent by now.
Sponsor: So we are on budget.
Project manager: Exactly on budget.
Finance: Then it is green. Next item.
Flight 214, Two Hours Out
Captain: Fuel check.
First officer: Two hours flown, two hours of fuel burned. Exactly on plan.
Captain: And where are we?
First officer: About two hundred miles behind the flight plan. The headwind is a lot stronger than forecast.
Captain: Then work it out. What do we land with?
First officer: ...Less than the reserve.
Captain: Right. We still have options, so let’s use them. Find us a fuel stop now, not in an hour.
Week 8, Steering Committee
Project manager: Again, we have spent exactly what we planned to have spent by now.
Sponsor: Good. So the software is ready for testing?
Project manager: The development budget has been fully used.
Sponsor: That is not what I asked.
Development lead: About half of the code is written.
Finance: But we are on budget?
Project manager: We are exactly on budget. We are just not done.
Sponsor: How long to finish?
Development lead: Another eight weeks. At least.
Nobody says anything for a while.
What do we Land With?
Both conversations started with the same sentence. Spent so far, exactly as planned. In the cockpit, that was the start of the check. In the Steering Committee, it was the end of it.
The first officer never claimed the flight was on track because the fuel burn matched the plan. Fuel burned only tells you what has happened.
The question that matters is what you will have left when you get there, and you can only answer it by looking at how far you have actually come.
Project reporting is mostly built on the first number. Actuals are what has been spent to date. The more sophisticated reports compare them with the budget to date, what we expected to have spent by now.
If the two match, the project is declared on track, and in most organizations that one comparison decides whether a project is green.
It says nothing about the work. A team that works exactly the hours it was scheduled for will hit the budget to the cent, whether it has written half the code or a quarter of it. Spending as planned is not the same as progressing as planned.
In week 4, a quarter of the code had been written. Anybody who asked could have known. If a quarter of the work took half the time, the whole job will take twice as long and cost twice as much.
That is the forecast. Not a feeling, just the same arithmetic the first officer did, with output instead of miles.
Actuals are the past. The forecast is the future. And project management is mostly about influencing the future.
The forecast was available in week 4, while there was still room to do something with it. Cut scope, add people, move the date, or stop.
By week 8, the testers have been booked, the go-live has been announced, and the business has planned around it. Every one of those options costs more, and some of them are gone.
Somewhere between week 4 and week 8, the project passed its point of no return. Nobody noticed, because the report was green.
Why does this keep happening? Because reporting is designed around the needs of Finance. Budgets are set before the year starts, actuals are booked every month, and at year-end the question that counts is whether the company stayed under budget.
A perfectly reasonable question for an accountant. It is a lot less interesting than whether the company got what it paid for.
The fix does not need a new tool. It needs a different first line on the report.
Put the forecast at completion at the top, in money and in time: what will this project have cost when it has delivered what it promised, and when will that be?
Base it on what has been delivered, not on what has been spent. Working code, features the users have accepted, or what was actually shown at the end of the last sprint.
Keep the actuals, because Finance needs them, but put them where they belong, underneath.
And if you sit on a Steering Committee, change the first question. Not “are we on budget?” but the captain’s question. What do we land with?
Flight 214 made its fuel stop and arrived fifty minutes late. Nobody remembers it.
The project landed in week sixteen. Everybody remembers it.